1st Author Team Meeting (ATM)
at Edinburgh University. |
Agreed scope of project and
contents of manual |
October 2005 |
UK Project Steering Group (PSG)
meeting at HR Wallingford (HRW) |
Agreed contractual details
and requirements of UK Environment Agency (EA) |
November 2005 |
1st PSG meeting at Schiphol |
Agreed outline of manual and
Calculation Tool |
December 2005 |
2nd ATM at Infram, Netherlands |
Established detailed structure
of Calculation Tool |
December 2005 |
2nd PSG meeting at BAW, Hamburg |
Critical review of first draft
of manual |
April 2006 |
3rd ATM at BAW, Hamburg |
Review of editing following
2nd PSG meeting |
April 2006 |
Produce 2nd Draft of Manual |
Edit manual
Review by PSG |
June 2006
from July 2006 |
1st version of Calculation
Tool |
Development and testing of
Calculation Tool components |
from July 2006 |
Publish Final Draft |
Edit manual following review
by PSG
Distribute final draft manual for designated end users’ comments |
November 2006
from December 2006 |
Calculation Tool online |
Beta testing of Calculation
Tool (password protected users) |
from February 2007 |
Completion of Manual |
Final edit of manual |
from April 2007 |
Completion of Calculation Tool |
Update Calculation Tool following
beta testing programme |
from April 2007 |
Production of Manual |
Bound printed version produced
and pdf available (registered users) |
June 2007 |
Calculation Tool and Website
go live |
The supporting website with
Calculation Tool, pdf of manual and supporting information
available to all registered users |
June 2007 |